PROJECT INFORMATIONS

Location: St-Hyacinthe
  
Owner:Beauward Shopping Centers Ltd.
  
Architect: NEUF - Antoine Cousineau 
  
Engineers: Leroux-Cyr
  
Contractor: DIVCO

Location: St-Hyacinthe
  
Owner:Beauward Shopping Centers Ltd.
  
Architect: NEUF - Antoine Cousineau 
  
Engineers: Leroux-Cyr
  
Contractor: DIVCO

The 50,000-strong city of Saint-Hyacinthe has been dubbed Canada's "agricultural science park" because of its thriving food production and biotechnology sector. However, until recently, Saint-Hyacinthe lacked a key element: high quality accommodation.

With the installation of the Sheraton Saint-Hyacinthe, the city has not only acquired a beautiful hotel, but also a gathering place for the community.

The new Sheraton property stands amidst the surrounding farmland of southern Quebec. With 205 rooms spread over 16 floors, it has quickly become the most important architectural structure of the city.

The first thing guests notice is the brightness and openness of the Sheraton lobby, which then naturally turns into the lobby of the adjoining convention hall.

The 50,000-strong city of Saint-Hyacinthe has been dubbed Canada's "agricultural science park" because of its thriving food production and biotechnology sector. However, until recently, Saint-Hyacinthe lacked a key element: high quality accommodation.

With the installation of the Sheraton Saint-Hyacinthe, the city has not only acquired a beautiful hotel, but also a gathering place for the community.

The new Sheraton property stands amidst the surrounding farmland of southern Quebec. With 205 rooms spread over 16 floors, it has quickly become the most important architectural structure of the city.

The first thing guests notice is the brightness and openness of the Sheraton lobby, which then naturally turns into the lobby of the adjoining convention hall.

A total of 2,336 prefabricated units were delivered to the site, weighing 7,400 tonnes. The exterior facade contained 3,400 square meters of architectural prefabricated reinforced concrete. The internal load-bearing walls consisted of 7,450 square meters of unstructured gray concrete. Internal load-bearing walls had concrete strengths of up to 60 MPa, while 45 MPa were required for the facade.

This project marks a turning point in the era of precast concrete in Quebec due to the construction of an 18-storey high building, more than 55 meters, 100% precast concrete for all structural elements, staircases and bearings as well as exterior cladding panels for anything above the ground floor level.

Beams and multiform columns, "H" load-bearing frames, shear walls, external panels in, punched and solid, some insulated (sandwiches), hollo-cored slabs, stairs and landings, are the main elements out of Schokbeton factories and Saramac for the realization of this flagship project. These elements were built prior to excavation work and foundations, simultaneously in our 2 factories, and then erected in a short period of time. This manufacturing process allowed the design and construction to overlap, which reduced the delivery cycle.

A total of 2,336 prefabricated units were delivered to the site, weighing 7,400 tonnes. The exterior facade contained 3,400 square meters of architectural prefabricated reinforced concrete. The internal load-bearing walls consisted of 7,450 square meters of unstructured gray concrete. Internal load-bearing walls had concrete strengths of up to 60 MPa, while 45 MPa were required for the facade.

This project marks a turning point in the era of precast concrete in Quebec due to the construction of an 18-storey high building, more than 55 meters, 100% precast concrete for all structural elements, staircases and bearings as well as exterior cladding panels for anything above the ground floor level.

Beams and multiform columns, "H" load-bearing frames, shear walls, external panels in, punched and solid, some insulated (sandwiches), hollo-cored slabs, stairs and landings, are the main elements out of Schokbeton factories and Saramac for the realization of this flagship project. These elements were built prior to excavation work and foundations, simultaneously in our 2 factories, and then erected in a short period of time. This manufacturing process allowed the design and construction to overlap, which reduced the delivery cycle.

The project, was completed in May 2018 for the precast portion, on time, despite delays of several months due to unexpected latent conditions.

Two shifts per day in installation have been set up to ensure the goal of getting ahead of a tight schedule. The average completion is a complete floor, structure, floor, concrete envelope, stairs and landings in one calendar week for +/- 10,000 square feet per floor. The prefabricated panels were installed immediately after the installation of the foundations. The building was closed and protected from the elements quickly which meant that the subsequent trades were on board more quickly.

The Concrete panels include structural capacity, insulation and architectural finish in an 8 "-12" panel, eliminating the need for coordination and construction of multiple trades that would have been required with other systems.

The project, was completed in May 2018 for the precast portion, on time, despite delays of several months due to unexpected latent conditions.

Two shifts per day in installation have been set up to ensure the goal of getting ahead of a tight schedule. The average completion is a complete floor, structure, floor, concrete envelope, stairs and landings in one calendar week for +/- 10,000 square feet per floor. The prefabricated panels were installed immediately after the installation of the foundations. The building was closed and protected from the elements quickly which meant that the subsequent trades were on board more quickly.

The Concrete panels include structural capacity, insulation and architectural finish in an 8 "-12" panel, eliminating the need for coordination and construction of multiple trades that would have been required with other systems.

This project confirms the advantages of prefabrication in terms of timing, ahead of the established one, but also reinforces the great qualities of the Total Precast Concrete system.

The savings in time generated by using Total Precast have had an advantage over costs. A shortened construction schedule means a reduction in the site's overhead costs (salaries, site development and utilities, among others) which results in significant savings.

In conclusion, it is a beautiful building that shows all the architectural and structural potential of precast concrete.

This project confirms the advantages of prefabrication in terms of timing, ahead of the established one, but also reinforces the great qualities of the Total Precast Concrete system.

The savings in time generated by using Total Precast have had an advantage over costs. A shortened construction schedule means a reduction in the site's overhead costs (salaries, site development and utilities, among others) which results in significant savings.

In conclusion, it is a beautiful building that shows all the architectural and structural potential of precast concrete.

Photos

Étapes d'érection Sheraton St-Hyacinthe - Erection steps Sheraton St-Hyacinthe - Schokbeton - Saramac