PROJECT information

Location: Dorval 
  
Duration of construction: 30 weeks of production and 64 days of installation 
  
Owner:Aéroports de Montréal 
  
Architect: Lemay et Associés 
  
Engineer: Nicolet Chartrand Knoll 
  
contractor: Aéroports de Montréal (ADM) 
  
Prefabricated components: 3 above-ground levels including: 
 ● 75 columns 
 ● 192 internal beams 
 ● 66 bracing walls, 23 624 square feet 
 ● 696 double T, 336 558 square feet
 ● 64 exterior spandrels, 19 141 square feet

Location: Dorval 
  
Duration of construction: 30 weeks of production and 64 days of installation 
  
Owner:Aéroports de Montréal 
  
Architect: Lemay et Associés 
  
Engineer: Nicolet Chartrand Knoll 
  
contractor: Aéroports de Montréal (ADM) 
  
Prefabricated components: 3 above-ground levels including: 
 ● 75 columns 
 ● 192 internal beams 
 ● 66 bracing walls, 23 624 square feet 
 ● 696 double T, 336 558 square feet
 ● 64 exterior spandrels, 19 141 square feet

DESCRIPTION

In the midst of the airport frenzy, it was necessary to maximally optimize the parking space, a task which was achieved by creating clearances of over 60 feet, thereby reducing the number of columns and making the area safer to circulate. Limiting the effects of construction on the daily activities of the airport was also a prerequisite.

In the midst of the airport frenzy, it was necessary to maximally optimize the parking space, a task which was achieved by creating clearances of over 60 feet, thereby reducing the number of columns and making the area safer to circulate. Limiting the effects of construction on the daily activities of the airport was also a prerequisite.

Photos